Sukut Construction was awarded the Salton City Landfill Phase 1B Cell Construction project located in Salton City, CA. This earthwork project consists of excavating and preparing of subgrade, placement of engineered fill material layers for berms around the cell expansion, placement of 2 ft thick low permeability soil liner, preparing the liner system subgrade, excavation and backfill of the synthetic liner anchor trenches, placement of the LCRS gravel, underdrain pipe, geotextile materials, and 2 ft thick protective soil cover material. The project is scheduled to begin January 2018 with the project completion date in April of 2018.

 

Client: 
Burrtec Waste Industries, Inc.
Location: 
Salton City, CA