Garland Solar

Client:
Recurrent Energy
Date Completed:
February 28, 2017
Location:
Rosamond, CA
Description of Project:

Sukut completed the site preparation on this solar project in three phases as a subcontractor to Signal Energy and CSI Electrical. The first phase scope included site clearing and leveling of 1,800 acres of land. Work consisted of removing existing vegetation to be re-used as mulch to minimize dust pollution, in addition to hydro-mulch. Roadway and water retention system construction. In the second and third phases, Sukut provided the trench excavation and backfill support. Project highlights included:

  • Developed and maintained the well water pump system
  • Cleared, grubbed and mowed 1,800 acres of vegetation
  • Graded 1,800 acres for the installation of solar arrays
  • Drill seeded and hydro mulched 1,250 acres
  • Graded 540,000 square feet of roadway
  • Provided dust control and dust mitigation measures for the 1,800 acre site throughout construction
  • Excavated and backfilled 95,000 linear feet of MV trenching
  • Excavated/backfilled 260,000 linear feet of DC Trenching