Lancaster Water Treatment Plant

Client:
County Of Los Angeles Sanitation
Date Completed:
April 24, 2014
Location:
Lancaster, CA
Description of Project:

Sukut constructed four, 70-acre wastewater treatment ponds. This project was designed as a balanced site. When the on-site material was excavated and reused, there was a shrinkage factor of 35 percent. This would have created a need for import material but with the use of GPS on the Sukut equipment, Sukut was able to facilitate the grades and compensate for the loss due to shrinkage and balance the site.
The following is a brief description of the work completed:
• Sukut performed all of the mechanical and electrical work in the pump station.
• Moved 1.9 million cubic yards of earth.
• Construction of four, 70-acre wastewater treatment ponds holding more than 1 billion gallons.