Sunshine Canyon LF Cell CC-4 P2 Liner Project

Client:
Republic Services Procurement, Inc
Date Completed:
December 29, 2017
Location:
Sylmar, CA
Description of Project:

Sukut completed a 5.8-acre cell construction, consisting of a five-layer liner system (two two-feet clay layers, one-foot LCRS gravel, one-foot sand, two feet of one-inch minus material).

Project highlights include:

  • 28,000 cubic yards of imported and placed clay soil
  • 7,000 cubic yards of LCRS gravel placed, along with 7,000 cubic yards of sand placed and imported
  • Installed 1,300 linear feet of LCRS HDPE pipe
  • 250,000 square feet of liner installation on both slopes and floor.