- Client:
- City Of San Diego
- Date Completed:
- January 31, 2004
- Location:
- San Diego, CA
- Description of Project:
-
Sukut Construction was contracted by the City of San Diego to perform final excavation of Module D and installation of impermeable geomembrane. This project is one of three phases Sukut Construction has completed for the City of San Diego at Miramar Landfill.
This work included 500,000 cubic yards of excavation in the stadium conglomerate formation, 75,000 tons of liner gravel, 2.2 million square feet of impermeable geomembrane, 165,000 cubic yards of low permeability clay and 165,000 cubic yards protective soil cover. Sukut self-performed 75% of the work.