CalContractor Magazine Features Sukut’s Phases I and II of Oasis In-Lieu Recharge Project

April 6, 2022

CalContractor Magazine highlighted Sukut’s Phases I and II of the Oasis In-Lieu Recharge project, the primary purpose of which is to provide more irrigation water to the surrounding communities from the Coachella Canal, in their March 2022 Underground Construction issue. As the existing water table was being depleted, the Coachella Valley Water District contracted Sukut in October 2019 to first construct a connection to the district’s canal distribution system as part of Phase I of the project. This work involved the construction of a 60-acre-foot concrete-lined reservoir and the installation of 2,835 linear feet of a 72-inch steel pipeline. Sukut also built an intricate bypass system and a reinforced concrete control structure that accommodated two 75HP vertical turbine pumps, motors, valves, and motor-actuated slide gates during the project. The work also included electrical conduit installation and surface restoration. Sukut completed this phase of the project in December of 2020.

The second phase began in March of 2021 and includes constructing approximately 17.5 miles of the pipeline of various diameter and underground facilities, including ancillary excavation, rock removal, trenching, shoring, dewatering, and surface restoration. Sukut is also constructing four pump stations with furnishings and installing vertical turbine pumps and backup generators, four reservoirs, and electrical control devices.

The construction of the reservoirs and pump stations is projected to be completed at the end of summer 2022. As the crews are working along and making good progress, the Phase II of the project is currently ahead of schedule and is expected to be complete this Fall.

 

To read the full article, starting on page 12 of CalContractor magazine, visit LINK

 

 

 

© 2024 Sukut Construction, LLC. All Rights Reserved.

Designed and managed by PushMyWeb

CALL NOW