El Sobrante Landfill Mine Reclamation and Cell 13B Excavation Project

The work is split up into two projects. The first project includes the excavation and stockpile for the future cell expansion of roughly 1,450,000 cubic yards with drainage installation on the stockpiles. The second project consists of the excavation of the old mine tailings of approximately 150,000 cubic yards, a property of about 500,000 cubic…Read more

Prima Deshecha Landfill, Infrastructure Phase 1A Project

Sukut is constructing additional on and off-ramps for Orange County Waste & Recycling to access their landfill off Avenida La Pata. In addition to this work, Sukut is constructing a 100,000-cubic-yard buttress and excavating an additional 130,000 cubic yards to stockpile to create a new working pad for a future energy plant facility. The infrastructure…Read more

Altamont Landfill FA2 Phases 6 and 7 Project

Sukut is working on this two-year contract that includes two phases of cell development at Altamont Landfill in Livermore, CA. Phase 6 consists of about 1.3 million cubic yards of excavation, which will go to stockpiles, as well as engineered fill. Phase 7 holds about 1.3 million cubic yards of excavation, with the majority going…Read more

OAL Landfill Gas Header Upgrade Phase 1 Project

On this project, Sukut is installing approximately 4,000 linear feet of 30-inch landfill gas header to upgrade the existing 18-inch header. This work includes a temporary landfill gas jumper system to keep the existing landfill gas system operational during construction. The project also involves the abandonment and installation of various existing landfill gas lines, butterfly…Read more

Landers Sanitary Landfill Phase 1A Project

Sukut constructed the Phase 1A cell expansion of the Landers Landfill for San Bernardino County. The project included 275,000 cubic yards of excavation, 350,000 square feet of geosynthetic liner installation, 5,000 linear feet of leachate collection and landfill gas piping, and 100,000 square feet of access road construction.Read more

FRB Landfill Phase VIII-A1 Groundwater Protection Project

Sukut is constructing the Phase VIII-A1 groundwater protection liner system at the Frank R. Bowerman Landfill. The project includes over eight million cubic yards of earthwork for the cell excavation, landslide remediation, and buttress fill placement. The project also involves 1.5 million square feet of geosynthetic liner installation, 25,000 tons of leachate collection gravel, 55,000…Read more

Colton Sanitary Landfill Project

The project includes the installation of four million square feet of 50 mil LLDPE geomembrane and closure turf, import of 140,000 cubic yards of soil, placement of 30,000 tons of aggregate base, paving 200,000 square feet of asphalt, drilling and installation of 6,700 vertical feet of landfill gas well, and installation of 22,630 linear feet…Read more

FRB Landfill Sewer and Water Line Treatment System Design-Build Project

The primary objective of this project is to contain Frank R. Bowerman landfill odors from the storage and treatment tanks and eliminate any associated odors when discharging the treated effluent to the sewer or during on-site reuse application. In order to meet this objective, Sukut is designing and constructing a treatment system that will reduce…Read more

Altamont Landfill FA2 Phase 5 and Compost Facility Contact Water Pond 2 Project

Sukut performed landfill improvements by excavating roughly 600,000 cubic yards of soil and rock, which included blasting approximately 150,000 cubic yards. The team placed 40,000 cubic yards of a clay liner, imported 50,000 tons of LCRS and underdrain gravel, and screened about 80,000 cubic yards of a one-inch minus material to complete the improvement work….Read more

© 2024 Sukut Construction, LLC. All Rights Reserved.

Designed and managed by PushMyWeb

CALL NOW